ROSCOMMON COMMUNITY COLLEGE / EDUCATION

Ardnanagh, Roscommon

A co-educational, multi-denominational community college, supported by Galway Roscommon Education and Training Board.


PROJECT DURATION

5 MONTHS

An 840sqm, 2-storey, low carbon in-operation expansion project that delivered a BCAR-compliant specialist classroom block, with a Building Energy Rating (BER) of A, and an air tightness test less than 1 m³/hr/m².

Mac Zero constructs 840m² specialist classroom block for Roscommon Community College in Ardnanagh, Roscommon.

PROJECT INFO

As part of the development of the Roscommon Education Campus, announced in 2021, funding was allocated for additional facilities to be commissioned for Roscommon Community College, including the provision of two SEN units.

Following a five-month design and build project, in August 2023, Mac Zero completed the handover of the new, two-storey block, which includes SEN provision and teaching space.

Finished in striking anthracite grey, the modern addition to the Roscommon Community College campus adds much-needed additional space and facilities for the college’s vibrant and growing school population.

In delivering the nearly zero-energy building (NZEB), a sensory garden, complete with soft play surfaces, was also designed and delivered by Mac Zero.

The 840 sqm classroom block was manufactured offsite, with the majority of site works taking place over the summer months to minimise disruption during the pupil’s academic year.

M+E PROJECT SPECIFICATIONS

Heating - Plumbing, ventilation and installation of a Split Air Conditioning Heating and cooling system. Room controls have been installed with ease of use in mind.

Plumbing - Boosted cold water is provided to all cold water outlets throughout the building with non-concussive taps to all wash hand basins within the toilet areas. Hot water is provided by efficient point-of-use water heaters, and accessible showers have been installed along with height-adjustable sinks.

High-end electrical fit-out, exceeding building control requirements.

Efficient LED light fittings throughout, with programmable PIR presence detection sensors.

Call alarm system and CCTV cameras throughout the building, connected to school's security system

MR MORGAN BOWLAND

ARCHITECTURAL PROJECT LEAD - BDP

“The Mac Zero team efficiently delivered outstanding results.”

“Over the duration of the contract, I collaborated with the Mac Zero team, and I must applaud their remarkable professionalism, quick turnaround, and proactive approach. They efficiently delivered outstanding results, exemplified by the impressive two-story building at Roscommon Community College”.

SITEWORKS

The new modular building was installed at the rear of the main school building. The main body of the on-site works was delivered during the summer holidays to minimise the impact on the school community. There was significant trenching and ducting required to connect electrical cable and IT services back to the existing school and these works were sequenced and carried out during school break with no disruption to the school.

A large pumping chamber was installed to pump foul drainage from the new building to the mains sewer which was situated approximately 100 metres away, and a SEN garden was delivered to the rear of the project, which overlooks a greenfield, tree-lined space, that’s adjacent to the school site. 

Internally, a hoist and assisted bench furniture were installed within the SEN space as stipulated in the terms of the project.